This feature enables you to carry out validations during the closure of a WBS Element or network activity. There is a new Business Add-in (BAdI) that is used to perform these validations.

Technical Details

Technical Name of Product Feature

ECC_60_PS_CLSD_VALIDATIONS

Product Feature Is

New

Country Dependency

Valid for all countries

Software Component Version

SAP_APPL 617

Application Component

PS

Availability

SAP ERP 6.0 Enhancement Package 7 (SP11)

Additional Details

This Business Add-In (BAdI) is used during the closure of a work breakdown structure (WBS) element or a network activity. The corresponding BAdI methods are used to carry out certain validation checks that are performed during the closure of the WBS element or network activity. If the validation checks fail, then the object does not get changed to the closed status.