Scheduling Dependent Operations According to the Scheduling Mode The following graphic shows an example for the rescheduling of an operation using the
insert operation scheduling mode
and the
scheduling dependent operations according to the scheduling mode
scheduling submode
. You have defined that the system should
maintain time relationships
.
You reschedule operation A10 to another date. Operation A10 is the
selected
operation, and resource 1 is therefore the
selected
resource. The system must shift operation B10 on the selected resource to a date in the future so that operation A10 can be scheduled on the new desired date. A10 and B10 have time relationships to further
dependent
operations on
dependent
resources 2 and 3. The system also reschedules these dependent operations with the
insert operation
scheduling mode in order that the relationships can be observed.