Backflush At planned order reporting points, and as required, you can go to the backflush transaction using fast entry backflush, in order to supplement the backflush data.
To display the backflush data in the detail area, use a detail profile, assigned to the detail screen BACKFL. For more information about the profiles, see
Preparatory Measures
. You select the detail profile in the
User Settings.
You insert the components Production Backflush .
Backflushing takes place at reporting points:
For line orientated production, you have defined reporting points for a line segment, a line network, in the line design within
Integrated Product and
Process Engineering
, and assigned reporting point types to them.Using the reporting point types, you can determine how the backflush should take place.
See also:
· For shop-floor-orientated production, you have maintained reporting points in the
Mode
,or modes for the activity in the process structure within
Integrated Product and Process Engineering
. If a mode of an activity has a reporting point, then the other modes must also have a reporting point assigned to them. The reporting point type must be the same for all modes within an activity, and for this reason it is maintained from the activity.
See also:
Maintain Action Points with iPPE (Shop-Floor-Orientated Manufacturing)
You have created a backflush profile. (Refer to Define and Set Default Values for Profiles ).
For further information about the prerequisites, see Backflush Proceerdure .
In
planned order management
, the functions of the production backflush are listed on the
Backflush
tab page
.
In the left area of the screen the following data for the selected planned order is listed:
all reporting points to be passed through
the backflush quantity (the maximum possible quantity which can be backflushed at that particular reporting point).
yield and scrap (previously backflushed quantities)
indicator
Active Mode
If alternative resources are available for an activity, the indicator is displayed using the
Active Mode
, where (with which mode) the activity is regularly to be executed. A backflush can not only be executed with the planned mode, but also with an alternative mode. The differentiation of the mode during backflush, works using the reporting point.
Note
If you backflush at a reporting point for a resource which is not indicated as being the active mode, the system sets that mode to active.
In the right area of the screen , you can enter backflush data for one of the selected reporting points in the left screen area:
Backflush quantity
Enter the quantity that you want to backflush.
Caution
When using the Rapid Planning Matrix(RPM), you can only backflush the total order quantity (generally 1). You cannot backflush partial quantities.
Note
You can also reverse a backflush. The cancellation is always a posting with a reversed movement direction. This means you enter the quantity, which you want to cancel with a negative sign.
Quantity indicator (yield or scrap)
Cause of the scrap, which was incurred during production
You specify a cause, if you have selected the scrap quantity indicator. Causes could be, for example, machine damage, operator’s failure, or a defect material.
Note
The cause indicator is specified in Customizing for the
Advanced Planner and Optimizer (SAP APO),
found under
You can backflush immediately (
Post Immediately
), or goto the backflush transaction (
Supplement Backflush
). The order data, and the previously entered backflush data are adopted at this point.
When the backflush is complete, the system updates the relevant order in the order overview.
Caution
If you set the status “final backflush”, the system cannot update the display in the order overview immediately. The cause of this, is that the indicator can only be set when all of the following processes in the SAP R/3 system are posted. When posting
asynchronous goods movements, this is dependent on the frequency, with which these goods movements are posted in the SAP R/3 system.
Synchronous goods movementsare update immediately. This includes the goods receipts and the materials for which you set the
Synchron.post GI
indicator in the product master in APO.
As the process for updating the backflush data runs independently to the updating of the display, you must manually update the order overview after a backflush (
).
For more information about a planned order, select the planned order in the
Order Overview
and choose
.
The system transfers the planned order to the detail area.
In the detail area, select the
Backflush
tab page.
Select a reporting point
Choose
.
A new screen area appears, on the right side of the tab page.
Enter the required backflush data.
If you wish to backflush the entered data immediately, choose
Post immediately.
If you wish to goto the backflush transaction, choose
Supplement backflush
.