Transferring Demands and Stocks for SMI
You can use report RSMIPROACT
or RSMIPROACT2
to transfer demand or stock data from SAP ERP to SAP SNC. You can run the report once a day in dialog mode (mainly for test purposes) or in the background, for example. The following procedure gives you an example of what kinds of data you can enter for a Supplier Managed Inventory
(SMI) business scenario.
The source list contains a valid entry for each selected SMI material.
On the SAP Easy Access
screen, choose .
Enter RSMIPROACT or RSMIPROACT2 in the Program
field and choose
(Execute
).
Choose SMI (Single Sourcing)
.
To switch off goods receipt references, choose
No Goods Receipt References
.
Enter the data shown in the table below:
Plant
MRP area
If you do not use MRP areas, add the same value as for the plant number in the field MRP Area
.
Material
If you use a special planning type for the material, enter the planning type.
Recommendation
We recommend that you set up a special SMI planning type to distinguish SMI materials from non-SMI materials.
Under Selection Parameters for Procurement
, you can enter additional selection restrictions for the material selection:
Instead of the planning type, the special procurement type can also serve as a criterion for distinguishing SMI materials from non-SMI materials.
The purchasing document type is a criterion that is checked in the second processing step when the source for the SMI materials has been determined.
Enter a selection time period for demands.
Choose Stock
.
Set the Consignment and Own Stock
indicator.
In the Send Parameters for IDoc
(RSMIPROACT
) or in the Data Transfer Parameters
(RSMIPROACT2
) screen area, enter the following data:
Field | User Action and Values | Notes |
|---|---|---|
| Enter a system. | Enter the name of the logical system to which the generated IDocs are transferred. This is usually the logical name of the EDI subsystem. The partner profiles refer to this logical system (see partner type |
| Set the indicator. | If you set this indicator, the system transfers the demand information to the IDoc or XML message. |
| Set the indicator. | If you set this indicator, the system transfers the stock information to the IDoc or XML message. |
| Set the indicator. | If you set this indicator, the system transfers the released QM inspection lot stock information to the IDoc or XML message. |
Choose
Execution.
Choose Update Run
.
Select the outbound interface, PROACT IDoc/XML (RSMIPROACT2
only).
Execute the report.
Enter the required data for running the report in the background.
Note
After executing the report, the system displays the results of the material and source determination.
Use the different tabs for displaying:
Sources (Supply Srce
)
Demand
Stock (material, vendor, storage locations, and stock figures)
Released QM inspection lot stock
Preview
The report uses the following symbols:
Symbol | Meaning | Notes |
|---|---|---|
| Valid source | The entry in the source list meets the required prerequisites. |
| The source is available in the source list but is not unique or is no longer valid. | If you have exactly one vendor for each material, set the |
| There is no relevant source in the source list. | Maintain the source list. |
| Consignment procurement | The item category of the source is |
| Regular procurement | The item category of the source is regular procurement. |
To create PROACT01
IDocs or ProductActivityNotification
messages, choose the Preview
tab, select or deselect materials, and choose Send Data
.
Note