Calculation of Lead Times in Inventory Planning
In inventory planning, the system performs the combined calculation of the economic order quantity (EOQ) and the safety stock (SFT). In doing so, the system considers the lead times of a product depending on the delivery scenario and on whether you plan to supply a location in your bill of distribution (BOD) with goods using push or pull deployment.
For the combined calculation of the EOQ and SFT you can choose whether you want to plan with the total DRP lead time or with the sum of the compound lead times below. If you want to plan with the DRP total lead time, you specify this in the service profile for the combined calculation of EOQ and SFT in the Use DRP PLT
field.
Note
The system can only consider your entry in this field if you work with the total lead time in DRP. Otherwise the system plans with the sum of the compound lead times below for the combined calculation of EOQ and SFT, irrespective of your entry in the Use DRP PLT
field.
Note
If you want to plan with the total lead time, the system also considers the goods receipt processing time as well as the total lead time, to calculate the minimum safety stock.
For more information about the service profile for the combined calculation of EOQ and SFT, see the Implementation Guide (IMG) for Advanced Planning and Optimization
under .
For more information about the DRP total lead time and the settings relevant for it, see Procurement Lead Times in Service Parts Planning in the section Total Procurement Lead Time
.
This lead time is the sum of the following component lead times:
Time between two planning runs
Plan approval and review time for distribution requirements planning (DRP)
Communication duration
Planned delivery time
Synchronization of start of goods receipt
Goods receipt processing time
This lead time is the sum of the following component lead times:
Time between two planning runs
Plan approval and review time for DRP
Communication duration
Planned delivery time
Throughput time of the CP
Transportation duration from CP to location
Synchronization of start of goods receipt
Goods receipt processing time
For more information about CPs, see Contract Packager.
This lead time is the sum of the following component lead times:
For locations with the Planned as Push
deployment indicator:
Throughput time of the location
For locations with the Planned as Pull
or Pull Only
deployment indicator:
Time between two planning runs
Goods issue processing time
Transportation duration from the one location to the other
Goods receipt processing time
This lead time only exists for locations with the Planned as Push
deployment indicator. It is the sum of the following compound lead times:
Throughput time of the CP
Transportation duration from CP to child location
Goods receipt processing time
This lead time is the sum of the following component lead times:
For locations with the Planned as Push
deployment indicator:
Throughput time of the location
For locations with the Planned as Pull
or Pull Only
deployment indicator:
Time between two planning runs
Goods issue processing time
Transportation duration from the location to the CP
Throughput time of the CP
Transportation duration from CP to location
Goods receipt processing time
This lead time only exists for locations with the Planned as Push
deployment indicator. It is the sum of the following compound lead times:
Throughput time at the CP of the parent location
Transportation time from the CP of the parent location to a second CP
Throughput time of the second CP
Transportation time from the second CP to the location
Goods receipt processing time
This lead time is for locations with the Planned as Push
deployment indicator and is the goods receipt processing time. This lead time is zero for locations with the Planned as Pull
or Pull Only
deployment indicator.
This lead time is for locations with the Planned as Push
deployment indicator and is the sum of the following compound lead times:
Throughput time of the CP
Transportation duration from CP to location
Goods receipt processing time
This lead time is zero for locations with the Planned as Pull
or Pull Only
deployment indicator.