Show TOC

 Assigning Line Activities with the Application List

Use

You can use the application list Line Bal. (Proc.Str) (Line Balance from Process Structure) to assign line activities quickly.

Procedure

  1. Choose Start of the navigation path View Next navigation step Application List Next navigation step Line Balance (Proc.Str.) End of the navigation path .

    In the detail area, the system displays input fields for you to select a process structure.

  2. Enter a line routing and, if applicable, class and class type when you wish to assign a complete process structure. Enter a line subrouting when you wish to assign a substructure.

  3. Choose Continue .

    The system displays a list of the activities in the selected process structure.

  4. Load the line balance.

    The line balance is displayed in the navigation area with the icon. In the application list, the symbol indicates activities that have already been assigned.

  5. Choose Expand to expand the line balance.

  6. To assign an activity with drag and drop, click on the activity in the list and drag it with the mouse until the mouse cursor changes to the symbol . Drag the activity to the required line segment or work area.

    The system displays a message saying that the line balance relationship will be created when you next save. The symbol in the application list indicates that you have successfully assigned the activity.

  7. Repeat step 6 until you have assigned all the activities.

  8. Then choose Save.

Result

You have maintained all the line balance relationships between the line elements and the activities.