Calendar Resource and Calendar Mixed Resource Resource whose capacity is not utilized during scheduling. The system only takes the calendar of the resource into consideration during scheduling.
In contrast to single resources, the following constraints exist for calendar resources and calendar mixed resources:
Since there is no capacity load for the calendar resource, it is not displayed in the Detailed Scheduling planning board .
The capacity of a calendar resource is not taken into consideration during scheduling of activities, so it cannot be scheduled finitely .
You cannot define a capacity profile for a calendar resource.
No setup time adjustment can be executed on a calendar resource.
In the following cases, you define a resource as a calendar resource.
You only want to take the resource calendar into consideration.
There are a lot of activities on the resource simultaneously; for example, on a handling resource for scheduling the goods receipt processing time. If you use another resource type, the system has to take the capacity into account when scheduling these activities, which may lead to performance problems.