Specifies necessary parameters for the MRP run planning horizon and displays preferences.
Note This topic documents fields and other elements in this window that either are not self-explanatory or require additional information. End of the note. |
Enter a description for the MRP scenario. |
Specify the start date (the first day of the first period) and end date (the last day of the last period) of the MRP planning horizon. MRP considers all the demands and supplies that have a due date falling within the planning horizon you define. The date range is automatically adjusted according to the period you define. Example You enter March 4, 2011 as the start date and March 15 as the end date of the planning horizon. Then in the View Data in Periods Of field, you specify 1 month. SAP Business One changes the two dates automatically to the beginning of the month, March 1, 2011 and the end of the month, March 31, 2011. End of the example. |
Define the length of each period, displayed in the MRP Results window, in days, weeks, or months, depending on the selected option. All MRP calculations are displayed in the defined time buckets. Note If you choose to group MRP results into period lengths other than one day, SAP Business One performs the MRP calculation on the first day of each period. MRP groups all the existing data for that period (supplies and demands) in the first day. The weekly numbering definition and weekend definition may affect the week numbers and the first day of the week. To maintain the definitions, chooseHoliday Dates Window. . For more information, see theEnd of the note. Example You make the following definitions:
Working Week 2 of 2011 starts on 3 January and ends on 7 January. The MRP performs the calculation for the entire week as if all of the business activity for the week happened on 3 January. End of the example. |
Displays the number of days/weeks/months of the planning horizon you define. Calculated automatically after you specify the start date, end date, and period definition. If you manually change the value of the field, MRP recalculates the value in the End Date field. |
Select the checkboxes to let MRP consider the holidays and weekends defined in Holiday Dates Window. SAP Business One automatically adjusts demands and supplies that fall into defined holidays or weekends. For items that require a certain period of lead time, considering holidays and weekends increases the lead time interval for MRP calculations. For more information about how holidays, lead time, and order interval jointly affect the MRO calculations, see Example: Holidays, Lead Time, and Order Interval in MRP.
For more information about the procurement method, see Item Master Data: Planning Data Tab. SAP Business One adjusts demands and supplies that fall into defined holidays or weekends following the rules stated below:
Example You have defined Saturday and Sunday as weekend and let SAP Business One consider holidays and weekends in MRP calculation.
End of the example. |
Select the sort criteria for the MRP report:
|
Displays the items without actual requirements after the MRP run. Items without requirements are items that, during the entire MRP horizon, have a sufficient quantity and do not require purchase orders, production orders, or warehouse transfer requests. If you do not select this checkbox, MRP items, without requirements or with incoming orders balancing the requirements, are not displayed. |
Defines this scenario as a simulation scenario. You cannot save recommendations or create production or purchase orders from simulation scenarios. |
Saves the MRP scenario at the current stage. Available only when you add a new scenario or update an existing one. Note You cannot save an MRP scenario if it is a simulation. End of the note. |
Runs the selected MRP scenario and goes directly to the MRP Wizard: MRP Results window. |