Procedure documentation Scheduling Manually  Locate the document in its SAP Library structure

Use

When you enter dates for a project element, the system carries out scheduling automatically when you carry out the next action in the system or press Enter on your keyboard. However, once you have released the project element, scheduling no longer takes place automatically for this project element because the system presumes that the dates are fixed from this point onwards and can only be changed in exceptional situations.

Prerequisites

      You are in the editing view of a project element you want to schedule.

      You have administration authorization for this project element and for its dependent project elements (lower-level elements and linked elements that are scheduled together with the current element).

Note

If you do not have the necessary authorization for the dependent project elements, the start dates of this element apply as fixed dates in scheduling.

Procedure

...

       1.      Choose Schedule.

The system calculates the dates of the selected project element as well as the dependent project elements again.

       2.      Save the changes.

 

See also:

Scheduling

 