This function defines which changes are to be made to a production order in order to take into account the change to a sales order or master data.
Sales order changes
To determine the changes, the system compares the Simulation Order with the production order that is to be changed.
Master data changes
The order objects that are to be changed are determined directly from the master data.
Note
To display the changes for a production order, choose ( ) Changes in the Overview of the Procurement Element Change Records . The screen Change Step Overview appears. There you can see which changes are allowed.
( )
For technical information about the determination of the changes refer to Executing a Comparison .
( )
Examples of changes that must be made to a production order:
Deleting an operation
Inserting a component
Reassigning a component
The execution of these process steps is described in Executing Process Steps .
See also:
Execution of the Comparison in customer enhancement COOCM002