You use this activity to start multiple SFC numbers by material in the POD. This feature is not supported in the Work Center POD.
The following table describes rules and settings that you can change for this activity in Activity Maintenance:
Rule | Setting |
---|---|
CONFIRM_PROCESSLOT_OPTIONS | REMOVE: Removes selected SFC numbers from the process lot automatically CANCEL: Does not remove the selected SFC numbers from the process lot CONTINUE: Allows the selected activity to continue without removing the SFC numbers from the process lot Default value: CONTINUE, REMOVE, CANCEL Note that if there are multiple setting values, the question dialog appears and the setting values displayed as action buttons. |
IGNORE_NOT_INQUEUE | YES: Starts only the SFC numbers that are members of the process lot that are in queue at the selected operation, and looks at the CONFIRM_PROCESSLOT_OPTIONS activity rule to determine if the confirmation dialog appears NO (default): Starts all SFC numbers in the process lot at the selected operation |
MAX_START_BY_ITEM_QTY | 100 (default): Specifies the maximum number of materials a user may execute at one time |
START_BY_ITEM | YES (default): Allows the user to start SFC numbers by material NO: Prevents the user from starting SFC numbers by material |
START_SORT_CRITERIA | HIGH_SFC_PRIORITY: Starts the materials with the highest priority first LOW_SFC_PRIORITY: Starts the materials with the lowest priority first LONGEST_TIME_IN_QUEUE (default): Starts the materials that have been in the queue for the longest amount of time first SHORTEST_TIME_IN_QUEUE: Starts the materials that have been in the queue for the shortest amount of time first |