 Parameters for Quantity Structure Control Locate this document in the navigation structure

Use

There are various ways to influence how a quantity structure is created. This section details the parameters with which you can control the quantity structure data.

Features

Quantity Structure Control

The quantity structure control controls how the system searches for alternatives when there is more than one BOM or routing for a material. You define the quantity structure control in Customizing and enter it in the costing variant. For more information, see Quantity Structure Control Through Customizing and Preparing for Material Costing .

Transfer Control

This determines

  • Whether a material is to be recosted, if costing data already exists for the material in the plant of the finished product

  • Whether costing data is to be transferred from another plant if the material is withdrawn from, or transferred to, this plant

You define the transfer control in Customizing and enter it in the costing variant. For more information, see Transfer of Existing Costing Data .

Reference Variant

The reference variant enables you to create a cost estimate using the quantity structure of an existing cost estimate as a base. The quantity structure of the cost estimate referenced is transferred and is not exploded afresh. You define the reference variant in Customizing and enter it in the costing variant. For further information, see Reference Costing .

Date Control

The system uses the date control to propose the date on which the routings and BOMs are exploded. You define the date control in Customizing and enter it in the costing variant. For more information, see Date Control .

The following figure shows how the costing variant combines all the control parameters for cost estimates. In addition to the other key parameters (such as the valuation variant and costing type), the costing variant contains the control parameters required for the quantity structure. These are the quantity structure control, transfer control, date control, and reference variant.

 ( )

Control Key in the Operation of the Routing

The control key of an operation in the routing specifies whether the operation is to be included in costing. You define the control key in Customizing and enter it in the operation in the routing. To cost the operation, you must set the Costing indicator. For more information, see Routings in Costing .

Note Note

Furthermore, you must mark the operation as relevant to costing (X) in the routing. Operations that are not marked as "relevant to costing" are ignored - even if the control key of the operation allows costing.

End of the note.

 ( )

See also:

For further information about the Customizing settings to determine the quantity structure, see the Implementation Guide (IMG) under   Product Cost Planning   Cost Estimate with Quantity Structure,   and Special Processing in Material Costing in the following sections:

  • Define Quantity Structure Control

  • Settings for Quantity Structure Control

  • Define Transfer Strategy

  • Define Date Control

  • Define Reference Variants

For further information about defining control keys, see the Implementation Guide (IMG ) under   Production   Basic Data   Routing   Operation Data   Define Control Key   .