 Completion of ABAP List-Based PI Sheets Locate this document in the navigation structure

Use

After you have fully processed a PI sheet, you can set the status of the PI sheet to Complete ; see Setting ABAP List-Based PI Sheets to Complete .

Prerequisites

A PI sheet can only be set to Complete if:

  • All entries required on the PI sheet have been made

  • All calculations have been carried out successfully

  • All the data on the PI sheet has been reported

Implications

When you set the status of a PI sheet to Complete , the system creates a message on the control recipe status (message category PI_CRST). This triggers the following changes:

  • The status of the control recipe is set to Processed .

  • The status of the corresponding order phases is set to Control recipe processed .

You need to set the status of your PI sheets to Complete or Technically complete if you want to:

  • Archive them via process data documentation