 Date Determination when an Order is Created Locate this document in the navigation structure

Use

The determination of dates depends on the order creation type. A production order is created by

  • Converting a planned order into a production order

  • Creating a production order manually

Features

Converting a Planned Order into a Production Order

If material requirements planning has already created a planned order for producing the material, the basic dates are copied from the planned order and the order start and finish dates are determined in a new scheduling run. If necessary, reduction measures are carried out.

Creating a Production Order Manually

If no planned order exists and you create the production order manually, the scheduling type determines which basic dates you have to enter.

If you enter both basic dates, the system tries to adhere to these dates when carrying out forwards or backwards scheduling. If necessary, the system also carries out reduction measures.

The following tables show which dates you have to enter and which dates are calculated via scheduling.

Date Determination Based on the Basic Dates

If the scheduling type specifies

you enter

scheduling calculates

forward scheduling

order start date

scheduled start scheduled finish order finish date

forward scheduling

order start date

order finish date

scheduled start scheduled finish

backward scheduling

order finish date

order start date scheduled start scheduled finish

backward scheduling

order finish date

order start date

scheduled start scheduled finish

only capacity requirements are determined

order start date

order finish date

scheduled start scheduled finish

today scheduling

no entry

order finish date scheduled start scheduled finish

today scheduling

order finish date

scheduled start scheduled finish

Date Determination Based on the Scheduled Dates (Production Dates)

If the scheduling type specifies

you enter

scheduling calculates

forward scheduling

scheduled start

order start date

order finish date

scheduled finish

forward scheduling

scheduled start scheduled finish

order start date

order finish date

backward scheduling

scheduled finish

order start date

order finish date

scheduled start

backward scheduling

scheduled start scheduled finish

order finish date

order start date

only capacity requirements are determined

scheduled start scheduled finish

order start date

order finish date

today scheduling

No entry

order finish date scheduled start scheduled finish

today scheduling

scheduled finish

order finish date

scheduled start

today scheduling

scheduled start scheduled finish

order finish date