You use this activity to split one SFC number into a new SFC number or several SFC numbers if the SFC quantity is greater than one in the POD (see Production Operator Dashboard (POD)).
Note
You cannot serialize SFC number if it is a member of an SFC group whose status is either Group Created or Sampling Active (see Sampling).
The ALLOW_ACTIVE_SFC_SPLIT activity rule is set to TRUE to allow an SFC number with the Active status to be split.
The following table describes rules and settings that you can change for the PR570 activity in Activity Maintenance:
Rule |
Setting |
---|---|
ALLOW_ACTIVE_SFC_SPLIT |
TRUE (default): Allows an SFC number with the status of Active to be split FALSE: Prevents an SFC number with the status of Active from being split |
AUTOMATIC_ID_GENERATION |
TRUE: Automatically generates new SFC numbers, using the SFC Release next number pattern in Next Number Maintenance The operator cannot assign new SFC numbers. FALSE (default): Requires the operator to enter the new SFC numbers in SFC Split The system does not generate the new SFC numbers. |
The following table describes rules and settings that you can change for the PR571 activity in Activity Maintenance:
Rule |
Setting |
---|---|
AUTOMATIC_ID_GENERATION |
TRUE: Automatically generates new SFC numbers using the SFC Release next number pattern in Next Number Maintenance The operator cannot assign new SFC numbers. FALSE (default): Requires the operator to enter numbers for new SFC numbers in SFC Split The system does not generate the new SFC numbers. |
To split SFC numbers, proceed as follows:
In the Qty to Split field, enter the quantity to split from the SFC number displayed in the SFC field.
Note
If SFC Split appears after you choose Log NC, the Qty to Split field is display only, and shows the quantity of SFC numbers you are nonconforming.
In the New SFC field, enter the SFC number you want the system to use to identify the new SFC number.
Note
If the AUTOMATIC_ID_GENERATION activity rule is set to TRUE, the system automatically generates new SFC numbers using the SFC Release pattern in Next Number Maintenance. The operator cannot assign new SFC numbers.
Choose Split.
Note
To split an additional quantity from the SFC number identified in the SFC field, repeat steps 1 through 3.
The system performs the split and displays information about the new SFC number in the table. The system adds a row each time you split an SFC number off the parent SFC number.