 Scheduling Types Locate this document in the navigation structure

A routing can be scheduled using the following scheduling types:

  • forward scheduling: The system schedules forward starting from the basic start date.

  • backward scheduling: The system schedules backward starting from the basic finish date.

  • "today" scheduling: The system carries out forward scheduling using the current date as a basic start date.

  • no scheduling: The individual operations are not scheduled. Based on the floats before and after production, the system calculates the scheduled start and finish and enters these dates in all operations.

The scheduling type determines which basic dates you have to enter. The following table shows the dates you must enter for the individual scheduling types as well as the dates that are then calculated using scheduling.

If you enter both basic dates, the system will make sure that the dates determined using forward or backward scheduling are within the specified period. If necessary, it will apply reduction measures .

Determining Dates in Routings

If the scheduling type is

and you enter the

the system calculates the

forward scheduling

basic start date

scheduled start

scheduled finish

basic finish date

 

basic start and basic finish dates

scheduled start

scheduled finish

     

backward scheduling

basic finish date

basic start date

scheduled start

scheduled finish

 

basic finish and basic start dates

scheduled start

scheduled finish

     

no scheduling

basic start and basic finish dates

scheduled start

scheduled finish

     

"today" scheduling

-

scheduled start

scheduled finish

basic finish date

 

basic finish date

scheduled start

scheduled finish

You can set up scheduling types for routings in Customizing for capacity planning under OperationsScheduling .