A routing can be scheduled using the following scheduling types:
forward scheduling: The system schedules forward starting from the basic start date.
backward scheduling: The system schedules backward starting from the basic finish date.
"today" scheduling: The system carries out forward scheduling using the current date as a basic start date.
no scheduling: The individual operations are not scheduled. Based on the floats before and after production, the system calculates the scheduled start and finish and enters these dates in all operations.
The scheduling type determines which basic dates you have to enter. The following table shows the dates you must enter for the individual scheduling types as well as the dates that are then calculated using scheduling.
If you enter both basic dates, the system will make sure that the dates determined using forward or backward scheduling are within the specified period. If necessary, it will apply reduction measures .
Determining Dates in Routings
If the scheduling type is |
and you enter the |
the system calculates the |
forward scheduling |
basic start date |
scheduled start scheduled finish basic finish date |
basic start and basic finish dates |
scheduled start scheduled finish |
|
backward scheduling |
basic finish date |
basic start date scheduled start scheduled finish |
basic finish and basic start dates |
scheduled start scheduled finish |
|
no scheduling |
basic start and basic finish dates |
scheduled start scheduled finish |
"today" scheduling |
- |
scheduled start scheduled finish basic finish date |
basic finish date |
scheduled start scheduled finish |
You can set up scheduling types for routings in Customizing for capacity planning under Operations → Scheduling .