 Cumulating Standard Values Locate this document in the navigation structure

Prerequisites

If the standard values of the suboperations are to be automatically cumulated to the main operation when you create the production order, you must set the Cumulation type key accordingly in the routing.

Alternatively, you can trigger the cumulation of standard values in the production order. A condition for cumulation is that you have maintained standard values at suboperation level.

Procedure

  1. Choose   Logistics   Production   Shop Floor Control   Order   Change   .  

  2. Specify the number of the order that you want to change.

  3. Choose  ( ) .

The initial screen for production orders appears. You can see the tab for production order data.

  1. Choose  ( ) .

You reach the operation overview.

  1. Select the operation for which you want to cumulate the standard values.

  2. Choose   Operation   Cumulate standard values  

Result

The standard values of the suboperations are added together and written to the standard values of the operation.