Show TOC

 Batch Splits Locate this document in the navigation structure

Use

If a material is managed in batches, you can carry out a batch split for every component.

This means that if you split a batch, you assign more than one batch to one component. In this case, each batch is displayed as a separate component in the component overview.

Note Note

Batch splits can only be triggered manually in the production order.

End of the note.

Prerequisites

The following requirements must be met for batch splitting:

  • The material master record of the material must specify that the material is managed in batches

  • Batches must exist for the material