Show TOC

 Revaluating Resource Planning Locate this document in the navigation structure

Use

If a resource refers to a specimen or material , and its price is changed, you must revaluate resource planning manually.

Procedure

To revaluate resources:

  1. In the planning menu for your application, choose Cost /   activity input   Change   Extras   Resource planning   Revaluate.  

  2. Specify which data is to be revaluated.

  3. To do this, maintain the following fields:

    Controlling area

    Version

    From period

    To period

    Fiscal year

    From resource

    To resource

  4. Choose Execute .

Result

The system posts the resource consumption using the updated price. You can check the results on the overview screen and on the period screen for planning.