 Copying Data to the Temporary File Automatically Locate this document in the navigation structure

Procedure

  1. From the routing menu, select the menu options   Extras   Material master   Schedule material master.  

  2. Enter the data for the materials, whose routings are to be scheduled.

  3. You do not necessarily have to enter a material on this screen. For example, you can select all materials for one planer group or in one plant.

     ( )

    Note that the material cannot have the material type KMAT . The procurement type cannot be external procurement . The procurement type is on the MRP 2 tab page of the material master.

  4. Make sure that neither the Update material master directly nor the U pdate with assembly scrap indicators have been set.

  5. Choose Enter .

The system schedules the routings and produces a results list with the scheduling results.

Result

The system saves the scheduling results in the temporary file. You can update the relevant material master records now or later.