From the routing menu, select the menu options
Enter the data for the materials, whose routings are to be scheduled.
You do not necessarily have to enter a material on this screen. For example, you can select all materials for one planer group or in one plant.
( )
Note that the material cannot have the material type KMAT . The procurement type cannot be external procurement . The procurement type is on the MRP 2 tab page of the material master.
Make sure that neither the Update material master directly nor the U pdate with assembly scrap indicators have been set.
Choose Enter .
The system schedules the routings and produces a results list with the scheduling results.
The system saves the scheduling results in the temporary file. You can update the relevant material master records now or later.