 Routings (PP-BD-RTG) Locate this document in the navigation structure

Purpose

Routings enable you to plan the production of materials (products). Therefore, routings are used as a template for production orders and run schedules as well as a basis for product costing.

Integration

In order to

You also require the components

Plan the usage of materials

Material master (LO-MD-MM)

Plan the use of work centers

Work centers (PP-BD-WKC)

Plan the external processing of operations

Purchasing (MM-PUR)

Plan quality inspections that accompany production

Quality planning (QM-PT)

Prepare cost calculation according to routings

Controlling (CO)

Plan and to document changes to routings

Engineering Change Management (LO-ECH)

Classify routings

Classification system (CA-CL)

Automatically calculate the planned values for the activities to be produced

CAPP Standard Value Calculation ( PP-BD-CAP)

In the SAP system, routings have the same basic structure as the following objects:

  • Master recipes

  • Inspection plans

  • Maintenance plans

  • Standard networks

Therefore, routings are cumulated with these objects under the superordinate term Task list .

Features

In a routing you plan

  • The operations (work steps) to be carried out during production

  • The activities to be performed in the operations as a basis for determining dates, capacity requirements, and costs

  • The use of materials during production

  • The use of work centers

  • The quality checks to be carried out during production