Show TOC

 Standard Values Calculation with CAPP on Order Creation Locate this document in the navigation structure

In the routing you can specify whether and how a CAPP standard values calculation is to be carried out on order creation. To do this maintain the following keys:

  • CAPP order :

You find this key on the screen Header Details in the section Control. It specifies whether standard values are to be recalculated on order creation and for which order categories. You can choose between the order categories "production order" and "planned order" or a calculation for both order categories.

Note Note

If you have used the key CAPP order to specify that a standard values calculation is to be carried out on order creation, then you must also maintain the key CAPP prod. order on the screen Operation Details for the individual operations for which standard values are to be calculated.

End of the note.

If there are already calculated standard values in the routing and

  • if you have maintained the key CAPP order , then the existing data is recalculated on order creation and, if necessary, updated for the order. The data in the routing remains unaffected.

  • if you have not maintained the key CAPP order , then the data already calculated in the routing is transferred to the order.

  • CAPP prod. order :

You find this key in the section CAPP on the screen Operation Details. It specifies whether the standard values calculation is to be carried out for the operation and whether it is to take place online or in the background. The key CAPP prod. order is, however, only taken into account if the key CAPP order is maintained on the screen Header Detail.

Note Note

With planned orders the calculation always takes place in the background even if the key CAPP prod. order specifies an online calculation.

End of the note.