Choose
Display.The system displays either the Change Additive Costs screen or the Display Additive Costs screen.
Enter the material and plant.
Enter the following data in the Costing data tab page:
Costing variant
Costing version
Costing date from
Choose ( ) Cost ests to find the required cost estimate.
The dialog box Selection of material cost estimates - additive costs appears. Enter the selection criteria required to find the additive cost estimate, and choose ( ) . A list of cost estimates corresponding to your search criteria appears. Choose the required cost estimate with a double click.
Choose ( ) .
The system displays either the Change Additive Costs screen or the Display Additive Costs screen. The costing information displayed is arranged in tab pages.
The following options are available:
( ) Takes you to the list screen of the unit cost estimate.
Note
You can only process the list screen if you have called up the function
.( ) Displays information about the cost estimate.
This will take you to the material master or costing variant, for example.
( ) Displays the itemization
( ) Displays the cost component split
( ) Partner Displays the partner cost component split
This function is only available if you have created a partner cost component split. A partner version must have been entered in the costing type.
See also:
For more information, see Analyzing the Results .