Use

You use this function to process future change records for confirmation processes (see Decoupling Processes Carried out During Confirmation ). You only need to process future change records in exceptional cases (for example, bringing processing forward, if the background job is scheduled for a later point in time). Future change records are normally processed as background jobs (see Goods Movements in Confirmations ). There are separate functions for processing goods movements with errors and errors in cost determination

Features

You decide which future change records should be read on the selection screen. By doing this, you can limit the selection of orders or processes.

You can use this function to process future change records from confirmations for the following processes:

  • Backflush

  • Automatic goods receipt

  • Actual cost determination

  • Data transfer to HR

You can execute the following actions:

  • Displaying an order for a future change record

    (Select the required record and choose  ( ) Order).

  • Displaying a confirmation for a future change record

    (Select the required record and choose  ( ) Confirmation).

  • Displaying details relating to a goods movement future change record

    (Select the required record and choose  ( ) Display Details for Goods Movements).

  • Executing backflushing/automatic goods receipt/actual costs determination

    (Select the required records and choose  ( ) ( Save )).

  • Executing data transfer to HR

    (Select  ( ) HR Data Transfer. You can only execute this action simultaneously for all records.)

    Note Note

    You cannot cancel confirmations that still have future change records.

    End of the note.

Activities

Choose   Logistics   Production   Shop floor control   Confirmation   Predefined processes.