 Work Scheduling Locate this document in the navigation structure

Prerequisites

Since work scheduling data is managed at plant level, you must enter a plant in the Organizational Levels dialog box to access the Work Scheduling screen.

Features

For information on:

  • Plant-specific material statuses

See Material Statuses .

  • Production versions

See Production Versions .

Activities

You can enter work scheduling times in one of the following ways:

  • By entering the setup time, interoperation time, and processing time for the material, as well as the base quantity to which the processing time relates. You do this under Lot size dependent in-house production time .

  • By entering the entire in-house production time, this being the sum of setup time, interoperation time, and processing time. You do this under Lot size independent in-house production time .

By choosing Versions , you access a dialog box where you can create production versions. For more information, see Production Versions .