You can use several different transactions available in the PI Sheet menu in process management to select PI sheets.
You can use the Find PI Sheets transaction for a general PI sheet selection . After calling the transaction, a selection screen appears on which you can enter your selection criteria. The worklist appears only after you have chosen Execute .
The following transactions are available for a specific PI sheet selection :
Worklist - Maintain
Worklist - Complete
Worklist - Check
In this way, the functions provided are tailored according to your role in the plant. The shift manager, for example, is mainly interested in checking and completing PI sheets, whereas the process operator is responsible for maintaining them. Each of the three worklists provides a special selection of PI sheets for the processing type you have chosen. When you choose Worklist - Complete , for example, the system only displays PI sheets that have status To be completed .
SAP has defined a selection variant and a display variant for each of the above-mentioned transactions. Each of the three selection variants for worklists is assigned to one user parameter . You can also define your own selection and display variants.
You can enter the user parameters in your user master record and assign the appropriate standard selection variant or your own selection variant to it. The selection variants themselves can have your own or standard display variants assigned to them.
You can create selection variants as follows:
In Customizing for Process Management by choosing Control Recipes/PI Sheets -> Selection Variants for PI Sheets -> Define Selection Variants for PI Sheets
On the selection screen of the relevant transaction by choosing Goto -> Variant -> Save as variant...
You can create display variants in the worklist's list overview.
For more information, see the SAP Library by choosing Getting Started -> Lists -> SAP List Viewer (ALV) Grid Control -> Display Variants .
You can enter user parameters in your user master record in Customizing for Process Management by choosing Control Recipes/PI Sheets -> Selection Variants for PI Sheets -> Assign Selection Variant to User .
Depending on the settings you have made in your user master record, one of the following screens appears after you have called the relevant transactions:
The selection screen containing predefined selection criteria for the processing type you have chosen. You can change these criteria. The worklist only appears after you have chosen Execute .
The worklist with the standard selection variant and the standard display variant
The worklist with the standard selection variant and your own display variant
The worklist with your own selection variant and the standard display variant
The worklist with your own selection variant and your own display variant
For information about the user parameters you can use and the criteria defined in the standard selection variants and standard display variants, see:
Selection Criteria for the Worklist
You can define the following criteria on the selection screen to define which PI sheets will be included in the worklist:
PI sheet data, such as:
The plant in which the PI sheet was created
The number of the control recipe from which the PI sheet was created
The operating group that is responsible for maintaining the PI sheet
The control recipe destination to which the PI sheet was sent
The date and time when the PI sheet was created
Mode of the PI sheet
Active PI sheets (no test)
Test PI sheets
Active and test PI sheets (all)
New
In process
To be completed
Canceled
Discarded
Completed
Archived (EBR)
Order data, such as:
Order number
The resource to which the PI sheet refers
Basic dates and scheduled start and finish
Further material-related data, such as:
The material to be produced
The batch to be produced
The inspection lot if a quality inspection is to carried out for the process order
In you want, a display variant that determines how the list is prepared for display in the worklist
Worklist Functions
The worklist is displayed in a table-like overview. In the worklist, you can do the following, for example:
Sort PI sheets according to different criteria
Display or maintain individual PI sheets
Delete PI sheets
For more information about the general list handling, see the SAP Library by choosing Getting Started -> Lists -> SAP List Viewer (ALV) Grid Control -> Display Variants .
Information in the Worklist
Depending on the type of worklist you have called, the following additional information is displayed for the individual PI sheets:
The Traffic lights icons in the Messages column indicate whether a process message was sent successfully for a PI sheet.
The icons mean the following:
Icons in Messages Column |
Meaning |
|
( ) No messages available |
No messages have been created so far. |
|
( ) All messages sent |
All messages have been sent. There may be messages with warnings. |
|
( ) At least 1 message to be sent |
- At least one message has been created but not yet been sent. - At least one message must be resubmitted. - At least one message must be resubmitted and contains warnings. |
|
( ) At least 1 message with errors |
At least one message could not be sent because: - It is incomplete - It could not be processed by one of the destinations - An error occurred and message processing was terminated. |
The message monitor provides information about the error that may have occurred. For more information about the process message statuses and their meaning, see Display of Process Message Lists .
The ( ) icon indicates that there are deviations in entries in the PI sheet.
The ( ) icon indicates that there is at least one comment in the PI sheet.