Show TOC

 Replacing Reference Operation Sets (Mass Replacement) Locate this document in the navigation structure

Use

You use this function to replace reference operation sets in all or multiple routings or rate routings at the same time.

Note Note

To enable accessibility for this transaction, set parameter ACC_MODE to X in the user profile.

End of the note.

Procedure

  1. In the area menu for   Routing MaintenancechooseExtras   Mass Changes   Reference Operation Sets   .

    The selection screen for replacing reference operation sets is displayed.

  2. To replace a reference rate routing , set the indicator Ref. rate routing .

  3. Specify the group and group counter of the old and new reference operation sets. Enter the increment to be used when the operations of the new reference operation set are inserted into the routing.

    Note Note

    If you have not set this parameter to X , you can select an overview variant. Choose Choose overview var. , enter the overview variant, and choose Continue.

    End of the note.
  4. Choose   Goto   Execute   .

    You see a list of all routings in which the old reference operation set/reference rate routing is included (where-used list).

    1. If necessary, you can specify a different reference operation set to replace the old one, instead of the one that you originally specified. Select the menu options   Settings   Replace with   .

      You reach the Default Values : Change dialog box.

    2. Enter the group and group counter of the new reference operation set/reference rate routing. Maintain the increment to be used when the operations of the new reference operation set are inserted into the routing. Choose Continue .

  5. Usually, the system replaces online . If you want to execute the replacement using batch input, choose   Setting   Change Replace Mode   (Batch Data Communication ). You can also use the replace mode to control whether certain screens are displayed for you to maintain during replacement.

    Note Note

    If you have not set the parameter ACC_MODE to X , you can change the data in the task lists, before you insert the new reference operation set everywhere.

    End of the note.
  6. Select all the task lists in which you want to replace the old reference operation set with the new one.

    If you want to select a number of objects at the same time, choose   Edit   Selections   .

  7. To replace the reference operation sets, choose   Edit   Replace.  

Result

The old reference operation set is replaced by the new one in all the selected task lists.

To see the current data in the where-used list, you must update the display.