You use the RESET_TOOL_HOOK
hook point activity to automatically change the resource status from Productive
to Enabled
after the tool was used to process and complete SFC number (see Tool Number Maintenance).
You can use this activity with the following hook points:
PRE_COMPLETE
or POST_COMPLETE
at the operation or resource level
PRE_DISP
or POST_DISP
at the NC code level