You use this activity to create and maintain routings in the system (see Routing).
This activity allows you to do the following:
Use graphical and tabular modes for creating routings (see Creating Routing Steps in the Graphical Mode)
Define the sequence of routing steps
Use operations with substeps in a Planning
or Production
routing
Associate a coded script with any branch in a routing
Configure nested routings
Configure disposition routings
Enter custom data values (see Custom Data)
Assign a routing to one or more materials for use with Production
shop orders ( see Material Assignment to Routing)
Assign a routing to a BOM/version for use with Production
shop orders
See also: Routing Maintenance Options
The following table describes rules and settings that you can change for this activity in Activity Maintenance
:
Rule | Setting |
---|---|
|
Note The starting sequence value must be a positive integer. The increment value must be a positive integer. A comma is the only valid separator. End of the note. If not defined, the existing system-generated defaults are used. |
|
Note The starting sequence value must be a positive integer. The increment value must be a positive integer. A comma is the only valid separator. End of the note. If not defined, the existing system-generated defaults are used. |
|
Note The starting sequence value must be a positive integer. The increment value must be a positive integer. A comma is the only valid separator. End of the note. |
| This rule allows you to use step IDs as sequence numbers for routing steps of complex routings with a lot of loops.
|
The following tables describe fields requiring explanation:
Field | Description |
---|---|
| The type of routing being defined
Note You can release SFC numbers only to the routing of the End of the note.
Note The system abbreviates the routing type as follows: Production routing – End of the note. |
| These fields appear if this routing record was initially created by retrieving an existing routing record and saving it with a different name or version. |
|
Users should not change the routing record.
The routing is no longer used.
The status is temporary. When the hold issue is resolved, users can change the status of the record. Note If the End of the note.
Note The following statuses are not applicable for the
End of the note. |
|
|
|
Note Released quantity will be added to the same SFC until the SFC quantity equals the lot size of the material. End of the note. Note
End of the note.
|
| The validity start date of the routing Note This field is visible only when the system rule End of the note. |
| The validity end date of the routing Note This field is visible only when the system rule End of the note. |
| Prints the document when an SFC number is processed on the routing |
| The group of disposition functions displayed to the operator at the end of a routing if no routings (such as |
| The BOM that contains components that you assign to a substep where components must be assembled Note Use this BOM only if you want to assign components to substeps. If you have specified the BOM, the system ignores the assembly operation in the BOM definition for the components. End of the note. |
|
Note
End of the note. |
Field | Description |
---|---|
| The step sequence assigned to the routing step |
| The operation assigned to the routing step |
| The reporting work center for the step |
| The step type assigned to the routing step |
| Opens the |