Background documentationEarned Standards Plug-In

 

You use this activity to view the scheduling standards and to view, claim or unclaim earned standards for an SFC number or a specific operation for an SFC number (see Earned Standards).

You can use this feature during the following processes:

  • Multiple operators work on the same SFC number at the same operation and each operator needs to claim standards for individual contributions

  • Tracking of operation partial completion for performance tracking and reporting purposes when operations have long processing times

  • Tracking of SFC number partial completion for performance tracking and reporting purposes, such as progress payments

Prerequisites
Rules

The following table describes rules and settings that you can change for this activity in Activity Maintenance:

Rule

Description

AUTO_AWARD_SETUP

YES: If any runtime standards are claimed, then all unclaimed setup standards are automatically awarded by the system.

NO (default): The claiming of runtime standards does not automatically award unclaimed setup standards.

AUTHORIZED_PERFORM_UNCLAIM

If set to TRUE, allows the user of this activity to perform the Unclaim action

PLUGIN_URL

Specifies the plug-in location in the SAP ME folder structure

Default value: /COM/SAP/ME/SCHEDULINGSTANDARDS/CLIENT/EARNEDSTANDARDSVIEWER.JSP

Fields

The following table describes fields requiring explanation:

Field

Description

Action Type

Allows you to select the Claim or Unclaim action

Data Entry Mode

Time Mode: Allows you to enter a new claim in time units

Percent Mode: Allows you to enter a new claim as a percentage of the scheduling standards time

Setup

Standard: Setup time defined for the material or operation/step in Scheduling Standards Maintenance, in the specified time units

Earned: The sum of setup claimed time and awarded time, in the specified units

Earned %: Setup earned time expressed as a percentage of setup standard time

Claim/Unclaim: The number of additional setup standards (expressed per the time unit or percent) requested to be claimed or unclaimed. Must be a positive number greater than zero. For unclaim, must be less than or equal to the standards earned.

Run

Standard: Runtime calculated from values for the material or operation/step in Scheduling Standards Maintenance, in the specified time units

Earned: The sum of run claimed time and awarded time, in the specified units

Claim/Unclaim: The number of additional run standards (expressed per time unit or percent) requested to be claimed/unclaimed. Must be a positive number greater than zero. For unclaim, must be less than or equal to the standards earned.

Total

Standard: The sum of the setup standard time and therun standard time, in whichever time unit is smaller

Earned: The sum of the setup earned time and the run earned time, in whichever unit of time is smaller

Earned %: Total earned time expressed as a percentage of total standard time

Claim/Unclaim

Allows you to save the entered changes to earned standards

Integration

When you use the Change Production feature to change the routing or material for an SFC number, the system attempts to move the standards accordingly. For more information, see Earned Standards.