You use this activity to indicate that physical work has been completed on an SFC number. The shop floor personnel submit the Complete
action after all physical work on the product has been completed. This action is recorded as an activity log record for the SFC number and is used to build the genealogy of the product. The activity provides validations at an operation and resource to confirm that the SFC number has completed all steps during the manufacturing at this operation.
The Complete
activity resets the selected resource from Productive
to the Pending
status when the last active SFC number is completed for the resource and the system has received a message from SAP Plant Maintenance
that the resource is now scheduled for preventive maintenance due to a measurement point usage counter. SFC numbers in the queue at an operation that is using this resource, cannot be started until the resource is in a Productive
status.
Note
The Complete
activity changes the routing step status to Complete Pending
for an SFC number in any of the following conditions:
There are open buyoffs for the SFC number
The SFC number is a member of an SFC group whose sampling results are not completed
There is a sample plan applicable for the SFC number at this point
SFC numbers in Complete Pending
status do not move to the next production operation and cannot be completed until any required sampling results are reported (see Sampling) and all buyoffs are closed.
The following table describes rules and settings that you can change for this activity:
Rule | Setting |
---|---|
|
Do not need to associate another button with the
|
| Determines whether to display an error when the operation or step is already completed or if the operator does not have the activity permission
|
| Default value: Note If you set multiple values, a dialog box is displayed with the values shown as action buttons. End of the note.
|
|
|
|
For more information, see Relaxed Routing Flow and NC Dispositioning |
When some SFC numbers in a process lot are not Active
at the operation (partial process lot) and the activity rule IGNORE_NOT_ACTIVE
is set to YES
, then the system acts as follows depending on the CONFIRM_PROCESSLOT_OPTIONS
activity rule settings:
CONTINUE
: Leaves all SFC numbers in the process lot and performs the Complete
action for the Active
SFC numbers at the operation
REMOVE
: Removes the selected Active
SFC numbers from the process lot and performs the Complete
action for them
CANCEL
: Cancels the Complete
action and displays an informational message
If left blank, displays dialog with Continue
, Remove
and Cancel
buttons
If two or more of nonblank settings are selected, displays a dialog with the specified settings as action buttons
If the activity rule IGNORE_NOT_ACTIVE
is set to NO
, the system cancels the Complete
action and displays an error message.
When the user completes a shop order where not all SFC numbers are Active
at the operation, the system acts as follows:
If the activity rule IGNORE_NOT_ACTIVE
is set to NO
, the system cancels the Complete
action, and displays an informational message.
If the activity rule IGNORE_NOT_ACTIVE
is set to YES
, the system leaves all of the SFC numbers in the shop order and proceeds with the Complete