You can use the DC520
hook point activity to check for all operations on the routing, up to and including the current operation, to ensure that the required data parameters for all associated DC groups have been collected for the current SFC numbers.
Note
This hook point activity ignores DC groups with the QM Inspection Group
checkbox selected (see Data Collection Maintenance).
Recommendation
To block sample SFC numbers with missing inspection data parameters, select the Block SFCs Until Inspection Finished
checkbox in Routing Maintenance
(see Routing Step Properties).
This activity is usually used with the PRE_START
, PRE_COMPLETE
, and POST_COMPLETE
hook points for an operation or resource.
The following table describes rule and settings that you can change for the DC520
activity in Activity Maintenance
:
Rule | Setting |
---|---|
|
|