Show TOC

Procedure documentationCreating Simultaneous Group with Dependent Steps

Procedure

  1. Fill out the fields on the Main tab page in Routing Maintenance to describe the routing and specify its characteristics.

  2. On the Routing tab page, do one of the following:

    • If you cleared the Tabular Routing checkbox on the Main tab page, drag a Simultaneous Group operation onto the drawing area and then drag the operations you want to include in the group onto the Simultaneous Group. Double-click the step to open its Properties screen, and assign successors to the appropriate routing steps. Choose OK.

    • If you chose the Tabular Routing checkbox on the Main tab, choose Insert New as required for creating table rows representing the operation you want to include in the Simultaneous Group. For each operation in the group, choose Simultaneous in the Step Type field.

  3. Fill out remaining necessary fields.

  4. Save your entries.

For more information about routings, see Routing Maintenance.