You can assign trigger points to operations in a routing or a production order.
Proceed as follows to create a trigger point in a routing:
You reach the Operation Trigger Points screen where any existing assignments are displayed.
The indicator... |
specifies that... |
Functions |
the trigger point triggers the functions you entered on the detail screen for trigger points (for example, release operation or include reference operation set). |
RelStop |
the operation is the last in a series of operations released by the trigger point. If the function release up to stop was triggered in a previous operation, all subsequent operations are released up to the operation with the RelStop indicator. |
You can set both indicators for a trigger point since both usages are possible.
You reach the Trigger Point Details screen.
You reach the dialog box Parameters for Function where you enter additional information, if necessary. Which fields appear in the dialog box depends on the function you selected. For example, if you selected "insert reference operation set", you have to enter the group and group counter of the reference operation set and the operation numbers between which the reference operation set is inserted.
Press Back to branch back to the detail screen.
The functions on the detail screen are effective only if you have set the functions indicator on the Trigger Point Overview screen.
-
the system status which triggers the function-
the status change which triggers the function ( reset status and/or set status)-
the once indicator if the function is to be triggered one time– the type of event which triggers the function (manually and/or by a change in status)
Creating a Trigger Point by Copying
For additional information about trigger points, refer to the