You must configure a system time point for a report. Before you define the system time points for a report, you must define a schedule for them. You define scheduling for the system time points by creating a background job for it.
Create a background job and define a schedule for it.
Define and subscribe the system time points for a report.
To define the schedule using background jobs, proceed as follows:
Go to transaction SM36.
Enter a name for the new background job in the Job Name field. For example, TP_BROADCASTING_ERPReport001.
Do not change the default values for Job class, Status, and Exec. Target.
Choose Start condition. The Start Time dialog box displays.
Choose Date/Time, and enter the values.
Check Periodic Job.
Choose Periodic Values.
Choose the schedule you want, and save your settings.
Choose Step from Define Background Job screen. The Create Step 1 dialog box displays.
In Program name under ABAP program, enter the following names to create two steps for the job with the following:
RSRD_BROADCAST_FOR_TIMEPOINT
/OSP/IW_TIMEPOINT_PROCESS
Choose Save, and from Job in the Define Background Job menu bar, choose Save.