Load Data Contents for InfoCube 0TMC_C06 Locate this document in the navigation structure

Process Chain Process Chain: 0PA_TMC_FULL_PFILL_C06

 

This process chain fills all data containers for the InfoCube Movements in Talent Groups (0TMC_C06) with data.

The following data containers are filled:

InfoObjects

For the following InfoObjects, hierarchy data, attributes, and texts, if available, are loaded:

DataStore Objects

InfoCubes

The process chain loads the complete data for the chosen period, therefore it may take some time to fill the aforementioned data containers. It is used to make the loading of data to the InfoCube Movements in Talent Groups (0TMC_C06) transparent.

To execute queries that are based on the MultiProvider Movements in Talent Groups (0TMC_MP06), the process chain must be adapted to meet customer requirements using process chain maintenance.

To reset the data containers, you have the process chain Delete Date Contents of InfoCube 0TMC_C06 (0PA_TMC_DELETE_PRESETC06) available.

Prerequisites

All data containers must be filled using replicated DataSources and be activated.

Note Note

If you activate the process chain, include only the minimum number of source systems required.

End of the note.

Process

This process chain has the following structure:

  1. The hierarchy data, attributes, and texts of the InfoObjects 0EMPLOYEE, 0HRPOSITION, 0ORGUNIT, and 0PERSON are loaded to the separate process chains Load Data for InfoObject 0EMPLOYEE, Load Data for InfoObject 0HRPOSITION, Load Data for InfoObject 0ORGUNIT, and Load Data for InfoObject 0PERSON.

  2. The process chain waits until the separate process chains have ended.

  3. The data for the DataStore objects 0TMC_DS03, 0TMC_DS09, and 0TMC_DS10 is loaded.

  4. The data for the DataStore object 0TMC_DS10 is transferred to the InfoCube 0TMC_C06.

Result

All data containers for the InfoCube Movements in Talent Groups (0TMC_C06) are filled with data for the chosen period.