Call up the order in change mode .
Edit the basic dates on the central header data screen for the order.
Edit the
scheduling type
on the
Additional data
tab page.
Edit the control key and the performing work center for an operation in the order on one of the following screens:
Operation overview of the order
Detail screen for general data
Detail screen for internal processing
Edit the execution duration for each operation on the detail screen for internal processing.
You have the following options:
The execution duration is automatically calculated by the system from other entries. You find the result in the
Duration
field on the detail screen.
You enter the execution duration manually.
Edit the
scheduling restrictions
on the
Dates
tab page.