You can make the following settings for bill of material selection:
Selection of alternatives/production version
You specify how the bill of material selection is to take place in the material master in the field
Alternative selection.
The bill of material can be selected by:
lot size
date
Production Version
If the selection is to take place using the production version then you must maintain the
production versions
and assign a bill of material alternative to each of these.
To maintain the material master choose
Bill of material usage
The bill of material usage is assigned to an order type. It groups together various parameters. The bill of material usage controls whether, for example, the bill of material is selected by date or by production version. You can also control for each application which bill of material status is checked during bill of material selection. For production orders you would get the system to check, for example, the status Released for order.
You maintain bill of material usage in Customizing for Shop Floor Control by choosing
You assign
bill of material usage
to an order type in Customizing for Shop Floor Control by choosing
.
Selection priorities
You can specify a selection priority according to which bills of material are selected with different usages. This priority is used if several bills of material with different usages exist for one material (for example, production BOM and engineering/design BOM).
The selection priorities are assigned to the individual bill of material application and define the priorities used to determine the bill of material usages during bill of material selection.
To maintain the data for the selection priority, choose
.
Selecting bill of material alternatives
If bill of material selection takes place according to the material master by date then you must maintain the validity periods for the bill of material alternatives.
You maintain the data for alternative selection in Customizing for Shop Floor Control, by choosing