To display master data, proceed as follows:
Branch to the header screen of the production order.
Choose
A dialog box appears where you can specify which master data can be read or for which explosion date it is to be selected.
Specify which master data must be read:
routing
BOM or
routing and BOM
If necessary change the explosion date for the BOM or the routing.
Note
If you want to read the master data with a particular revision status then you can leave out this step: The system copies the date from the revision status in this case.
You can also specify the following data:
a production version to select the relevant BOM or routing alternatives
a revision status
Note
If no production version or revision status is maintained for the material to be produced then the corresponding field is not displayed in the dialog box.
Choose .
The system chooses the selected master data again according to the specified criteria .