In Customizing, the following priorities are assigned for plant
0001
and order type
PP01
:
Priorities for Routing Selection
Task list type |
Use |
Status |
1. N |
Electronics |
Released |
2. N |
Electronics |
Created |
3. N |
Production |
Created |
In this case the system first looks for a routing with the usage electronics and the status released. If it does not find a routing that fulfills these criteria it looks for a routing with the usage electronics and the status created. If it does not find a routing that fulfills these criteria it looks for a routing with the usage production and the status created.
If, in spite of these priorities, it is not possible to select a routing, the system reads all the routings that exist for the material at the explosion date that should be selected according to the selection ID. You must then choose a routing manually from this list.