If you are using PRTs (production resources/tools) for an order, you often do not need them for the entire duration of the operation. For this reason, you can schedule single PRTs individually within the dates defined for the operation.
Select the required order, call up the operation overview, and select the required operations.
Choose PRT
.
The PRT List for Operation
screen appears for the first operation selected.
Select the required PRTs on the PRT List for Operation
screen and call up scheduling using .
The system displays the sections Scheduling data
and Dates for PRT usage
for the first PRT selected.
Make all the necessary and desired entries in the Scheduling specifications
section and confirm your entries with Continue
.
The system places the calculated scheduling dates in the section Dates for PRT usage
. Check the dates and make any changes required to the scheduling specifications.
Call up any other PRTs selected using
.Return to the PRT List for Operation
screen. Process the PRTs for additional operations, as required.
Return to the operation overview and save the order.