Show TOC

 Revaluating Resource Planning

Use

If a resource refers to a specimen or material , and its price is changed, you must revaluate resource planning manually.

Procedure

To revaluate resources:

  1. In the planning menu for your application, choose Cost / Start of the navigation path activity input Next navigation step Change Next navigation step Extras Next navigation step Resource planning Next navigation step Revaluate. End of the navigation path

  2. Specify which data is to be revaluated.

  3. To do this, maintain the following fields:

    Controlling area

    Version

    From period

    To period

    Fiscal year

    From resource

    To resource

  4. Choose Execute .

Result

The system posts the resource consumption using the updated price. You can check the results on the overview screen and on the period screen for planning.