Show TOC

 Executing Partial Conversion of Planned Orders

Prerequisites

To execute a partial conversion for a planned order you must first branch to the screen for query subset/order correction. Here you have the following options:

Shop Floor Control

  1. Choose Start of the navigation path Logistics Next navigation step Production Next navigation step Shop Floor Control Next navigation step Order Next navigation step Create Next navigation step From planned order Next navigation step . End of the navigation path

  2. The initial screen Create production order appears.

  3. Enter the required data.

  4. Set the partial conversion indicator and choose .

You reach the screen Query subset/order correction .

Current Stock/Requirements List

  1. Choose Start of the navigation path Logistics Next navigation step Production Next navigation step MRP Next navigation step Evaluations Next navigation step Stock/requirements list Next navigation step . End of the navigation path

  2. You reach the screen Current stock/requirements list.

  3. Enter the material to be manufactured and the plant. Choose .

  4. Double-click the required planned order to call it up and choose ->PartConvProdOrder.

You reach the screen Query subset/order correction .

MRP List

  1. Choose Start of the navigation path Logistics Next navigation step Production Next navigation step MRP Next navigation step Evaluations Next navigation step MRP list - material Next navigation step . End of the navigation path

  2. The initial screen MRP list appears.

  3. Enter the material to be manufactured and the plant. Choose .

  4. Double-click the required planned order to call it up and choose ->PartConvProdOrder.

You reach the screen Query subset/order correction .

Material Requirements Planning

  1. Choose Start of the navigation path Logistics Next navigation step Production Next navigation step MRP Next navigation step Planned order Next navigation step Convert to ProdOrd Next navigation step . Next navigation step Partial conversion. End of the navigation path

  2. The initial screen Create production order appears.

  3. Enter the required data.

  4. Set the partial conversion indicator and choose .

Procedure

The rest of the procedure is the same in all cases above:

  1. If you want to execute several partial conversions choose .

  2. Specify the desired dates and quantities.

Note Note

During conversion, the system uses the scheduling type that is specified for the order type and plant entered in Customizing for Shop Floor Control, by choosing Start of the navigation path Operations Next navigation step Scheduling Next navigation step Specify Scheduling Parameters Next navigation step . However, this can be changed once the conversion to the individual orders has taken place. End of the navigation path

End of the note.
  1. Choose Generate .

The system generates a production order for each line. Since the orders created have not yet been saved you at first receive temporary order numbers (for example, %0000000001).

Note Note

As soon as a partial quantity has been converted to a production order the corresponding line in the screen can no longer be deleted. If you want to delete this, you must leave the transaction and execute a new partial conversion.

End of the note.
  1. If you want to make more changes to a created order, select the line and choose .

The screen Create production order: Header appears.

Once you have made the changes, choose to branch back to the Query subset / order correction screen .

  1. Choose .

Result

The system saves the production orders created.

If the total quantities of the created production orders is less than the remaining planned order quantity and the indicator Delete planned order has not been set, the planned order quantity is reduced accordingly.

If the total quantity of the created production orders is greater than or equal to the remaining planned order quantity, the planned order is deleted.