 Dispatching and Deallocating Without the Planning Board

Use

You can use this function to:

  • Dispatch or deallocate operations

  • Deallocate all operations of a production order

Dispatching

Proceed as follows when dispatching:

  1. Dispatch an operation. The operation receives the status DSPT (dispatched). The capacity requirements are planned without capacity leveling.

  2. The system issues a warning if a capacity is overloaded.

  3. If necessary, change the operation dates of the dispatched operation (operation tab, Dates tab page).

  4. Midpoint scheduling is used when the order is rescheduled. The dates of the dispatched operation are not adjusted.

Activities

  • To dispatch an operation, select Start of the navigation path Operation Next navigation step Dispatch End of the navigation path on the operation overview (select operation) or on the tab page.

  • To deallocate an operation, select Start of the navigation path Operation Next navigation step Deallocate End of the navigation path on the operation overview (select operation) or on the tab page.

  • To deallocate all operations of a production order, select Start of the navigation path Functions Next navigation step Deallocate. End of the navigation path

See also:

Executing Capacity Leveling (SFC)

Capacity Leveling in Shop Floor Control