You can use this function to:
Dispatch or deallocate operations
Deallocate all operations of a production order
Dispatching
Proceed as follows when dispatching:
Dispatch an operation. The operation receives the status DSPT (dispatched). The capacity requirements are planned without capacity leveling.
The system issues a warning if a capacity is overloaded.
If necessary, change the operation dates of the dispatched operation (operation tab,
Dates
tab page).
Midpoint scheduling is used when the order is rescheduled. The dates of the dispatched operation are not adjusted.
To dispatch an operation, select
on the operation overview (select operation) or on the tab page.To deallocate an operation, select
on the operation overview (select operation) or on the tab page.To deallocate all operations of a production order, select
See also: