There are two ways to schedule partially confirmed operations:
Partially confirmed operations
A partially confirmed operation is scheduled forwards starting from the actual finish date. Only the
remaining duration
is scheduled.
The remaining duration of an operation is calculated according to the following formula:
Remaining qty = original qty - actual qty
To calculate the duration of the operation segments, the remaining quantity and the forecast values are entered into the formula. If no forecast values were entered in the confirmation, the remaining quantity and the standard values are entered
Shift order
You can set the
Shift order
indicator for scheduling partially confirmed orders (Customizing for
Shop Floor Control
by choosing
). This indicator causes the order to be shifted to a new date. The system carries out scheduling using the
remaining duration
of the operations, which means that the actual dates of the operations are no longer taken into account. The system schedules starting from the basic dates of the order using the remaining duration of the operations. The original setup duration is used for scheduling.