In the group box
Clearing
, you edit those fields of a condition that are included in
Date Category 220020 Clearing
You can make the following settings when editing a condition with the date category
220020 (Clearing)
.
You can define a
working day shift
for the clearing date. The working day shift specifies whether, and by how many days, a date is to be shifted if it falls on a Sunday or a public holiday. If you want to use the working day shift, you must specify at least one calendar for the working day shift
.
There are up to five calendars that the system uses to determine a working day for the working day shift
.
A working day must be a working day in all the calendars.
The date update must be one of the following:
Periodic
Relative
An annual block of appointments