Use
You use this procedure if you want to copy an operation without its subordinated or assigned objects (such as sub-operation, component assignment and so on).
Prerequisites
The task list header and sequence to which you want to add the operation must already exist.
Procedure
The EWB: Copy – Target data dialog box appears.
The EWB: Assign new operation number dialog box appears. The system proposes an operation number that has not yet been assigned. You can either accept or change this number.
The system then creates the copied operation in your worklist and locks it for other users. You can see this from the lock symbol.
Result
The system creates a copy of the operation in the database.