Start of Content Area

Procedure documentation Referencing a Work Center Operation Set  Locate the document in its SAP Library structure

Procedure

  1. Call up the EWB: Operation overview screen.

Note

If you are using a rate routing instead of a normal routing you should count "routing" to mean "rate routing" and "reference operation set" to mean "reference rate routing" in the following steps.

  1. In the context, enter the identifying data for the routing and sequence in which you want to reference the work operation set.
  1. Choose Operation ® Create reference to work center op. set . If the EWB: Process using dialog box appears, you have to enter either a key date or a change number.

The EWB: Reference Work Center Operation Set dialog box appears.

  1. In the Work center operation set screen area, enter the task list group and group counter, of the reference operation set that you want to reference as a work center operation set.
  1. In the Reference screen area, enter the operation number for the plant and work center to which the reference operation set is referenced as a work center operation set.

Note

You can either except any default values offered by the system or enter your own values.

  1. Click This graphic is explained in the accompanying text.

You return to the EWB: Operations overview screen. The system displays the referenced work center operation set.

  1. Save your data.

Result

The system creates the work center operation set in the database.