Making a Multi-Level Copy of a BOM Header
Use
You use this procedure if you want to make multi-level copies of a BOM header.
You must use this procedure if you want to copy items and subitems as well.
Prerequisites
The material under which you want to make a multi-level copy of the BOM header must already exist.
You have selected the
copy range so that the desired object types (or at least the object type BOM header and, for example, the object type Item) are copied as well. For more information, see Editing the copy range.Procedure
The EWB: Copy – Target data dialog box appears.
To check or change the copy range click Copy range.
The system creates the multi-level copy of the BOM header in the worklist. This means it copies the BOM header that you make a multi-level copy of as well as the sub or assigned object types to the BOM header, provided they have been inserted in the copy range .
Result
The system creates the multi-level copy of the BOM header and the objects included in the copy, in the database.