This function enables you to simultaneously process an item in several of the following types of BOMs:
Simultaneous processing takes place using item assignments to different alternatives or variants. With the help of group maintenance you can avoid multiple maintenance of BOM items and therefore reduce you work time.
Prerequisites
Group maintenance is activated in Customizing the Engineering Workbench under Editing working areas. For the working areas selected there, or those newly defined, you have to set the BOM indicator in the Group processing screen.
In the Engineering Workbench you can check whether you work with or without group maintenance in the following way:
In the initial screen EWB: Selection criteria for <Focus of your working area> select the symbol in the screen area Working area.
The EWB: Working area details dialog box appears.
If the BOM indicator is set in the Group processing screen area then you work with group maintenance. If the indicator is not set then you work without group maintenance.
Features
Within group maintenance you have the following options:
Activities
You want to |
The system |
Create an item with group maintenance |
Creates the item in all of its assigned alternatives/variants |
Change an item with group maintenance |
Changes the item in all of its assigned alternatives/variants |
Delete an item with group maintenance |
Deletes the item (and all its sub-items) in all its assigned alternatives/variants |
Copy an item with group maintenance |
Copies the item (and all its sub-items) in all its assigned alternatives/variants |
Creates assignments in group maintenance |
Creates assignments for all selected alternatives/variants |
Deletes assignments in group maintenance |
Deletes assignments for all selected alternatives/variants |
Deactivate/activate group maintenance |
deactivates/activates group maintenance |
Note that when copying and deleting items with group maintenance, both the item itself and the relevant subordinated subitems, are copied or deleted in all alternatives/variants to which the item is assigned.
If an item that was created with group maintenance and that has several assignments, is further processed with deactivated group maintenance then this item is exploded in the item overview with the same item ID and the same item number according to the number of created assignments. This means that the item processed further without group maintenance is separately listed for each alternative/variant to which it was assigned with group maintenance. Changes to the item then only take effect in the alternative/variant selected for the change.
For a better understanding of the maintenance of items it is recommended that you do not change your processing method (so with or without group maintenance).